Selectmen Approve Hybrid Night/Day Work Schedule for Eversource on Greenwich Ave: “Spreading the Misery”

The Selectmen approved a hybrid work shift schedule of 3 nights and 2 days for loud test pit digging Greenwich Ave between Grigg St and Railroad Ave. The start date for the work will reflect the issuance of permits. The test pit work is estimated to take 3-4 weeks to complete. Depending on what obstacles the test pits reveal, installing an electrical duct from Grigg to Railroad/Bruce Park Ave could take about six weeks. Continue Reading →

Filed under:

Greenwich Green & Clean to Host Spring in Bloom Fundraiser to Support Summer Hanging Flower Baskets

Greenwich Green & Clean is hosting its Spring in Bloom Fundraiser on Sunday, May 18, from 3:00pm to 5:00pm at The Field Club of Greenwich. The event aims to raise crucial funds for the maintenance of Greenwich Green & Clean’s signature project – the summer flower baskets hanging from the lampposts throughout Central Greenwich. Continue Reading →