On Friday morning Joe Siciliano gave an update on the Binney Park pond dredge project while subbing for Peter Tesei on the Ask the Selectman radio show on WGCH 1490.
Siciliano said first the pond was first de-watered and currently materials are being removed. He said concrete basins will be constructed to catch some of the materials.
“The overall goal is to have it finished this fall, in October or November, with a goal of having it completely reopened by next spring.”
“People should be seeing some progress over there. They are making great strides,” He said.

Binney Park pond dredge project involves de-watering the pond and pumping water around it. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager

Pond dredge materials stuck to chain link fence around Binney Park pond. Sept 9, 2017 Photo: Leslie Yager

Binney Park pond dredge progress. Sept 9, 2017 Photo: Leslie Yager