The new Central Middle School project, a two-phase 21-acre campus project, is being constructed in phase one.

June Look-Back
● Poured slab-on-grade concrete for part of the 2nd floor
● Started erecting the steel structure of the school building
● Began masonry for gym walls
● Continued foundation wall systems, waterproofing, and backfilling operations

July Look-Ahead
● Continue structural steel erection
● Continue foundation systems, gym masonry walls, and backfill operations
● Start installing sewer lines outside the building and connect them to Town sewer at Indian Rock Lane
● After steel is installed:
○ Perform Underground mechanical, electrical, and plumbing (MEP) installations
○ Continue pouring concrete floors (slab-on-grade and slab-on deck)
● Start work on the outside walls
● Construction work will also take place on Saturdays from July 12 and through next month
● The truck route remains as Stanwich Road to Orchard Road, regardless of school being out of session and has performed well

contributed photo

contributed photo

If you have a safety concern, please contact the Turner Construction personnel Joseph Phelan, Project Manager (203) 410-0874 <[email protected]> or Chris Chila, Project Superintendent (860) 634-7216 <[email protected]>