Greenwich Public Schools issued an update on the construction of the new 135,000 square foot Central Middle School.

The CMS campus is 21 acres, which allows for the new building to be constructed adjacent to the original 1958 structure, in a two-phase project. The project involves demolition of the existing building once the new building is completed.

The new school is designed for 660 students in approximately 125,000 gross sq ft in a two-story structure, with the potential for flexibility to serve up to 720 students. The estimated cost of the project is $112 million. The state is expected to provide about 20% in reimbursement. The project is anticipated to be completed on time in August 2026.

Completed in November
● Substantially completed placement of slab on grades for building
● Substantially completed exterior framing and sheathing
● Substantially completed roofing system installations
● Continued exterior AVB (air and vapor barrier) installations throughout
● Continued installation of exterior façade
● Started drywall installations at 2nd floor classroom spaces
● Continued above-ceiling MEP (mechanical, electrical, and plumbing) installations at the lower level
● Continued storm utilities around site

December Look-Ahead
● Substantially complete exterior AVB systems
● Continue site utilities and utility corridor
● Continue exterior façade installations throughout
● Continue above-ceiling MEP installations at lower level
● Continue drywall at 2nd floor classroom spaces
● Start above-ceiling and classroom finishes
● Delivery and placement of mechanical room equipment

A construction update from the district notes that under Greenwich’s noise ordinance, Turner Construction may work past 6:00pm, by monitoring and complying with residential decibel limits at property lines.

The project has also received temporary exemptions to the Town’s noise ordinance, permitting Saturday morning work and holiday activity through December. These exemptions are submitted monthly when needed.

If you have a safety concern, please contact the Turner Construction personnel Joseph Phelan, Project Manager (203) 410-0874 <[email protected]> or Chris Chila, Project Superintendent (860) 634-7216 <[email protected]>

The in-wall inspection process for the second floor classrooms have begun. Installation of drywall has started. Photo: Greenwich Public Schools.

New Central Middle School auditorium seating space with the stage area in the background. Photo: Greenwich Public Schools.